Initial Startup
NOTE: Some on-site assembly may be required prior to
initial startup. See assembly drawings for more informa-
tion.
1. Go through the Pre-Operation Checklist in the fol-
2.
lowing table.
✔ Checklist
System Grounded
Verify all grounding connections were made. See
Grounding, page 6.
All connections are tight and correct
Verify all fluid, air, and system connections are
tight and installed according to the supplied sche-
matics.
Air supply valves are open
Verify all Incoming Air Ball Valves are open.
Fluid supply valves are open
Verify all Fluid Line Ball Valves are open.
2. Close all ball valves and all other valves within the
feed systems.
3. Place an in-line regulator and shut-off valve
between the machine and the air supply.
4. Connect a 3/8 in. or larger diameter air supply line to
the air inlet.
5. Connect the required electrical power to the
machine as indicated on the identification name-
plate and logic drawings.
6. Check the tightness of all fittings.
313904B
Initial Startup
11