Operation; Sequence Of Operation - Graco PD44 Operations & Parts List

Metering valve for high wear material
Hide thumbs Also See for PD44:
Table of Contents

Advertisement

Operation

Operation
The operation of the PD44 metering valve is controlled
by an external source.

Sequence of Operation

Step 1: Reload
Spools shift to the right
Material feed inlets (A,B) are opened
Materials are transferred into the metering cham-
bers by a pressurized feed system
Outlet ports are blocked
Metering rods (E) are retracted to a precise position
determining the volume of each material
Step 2: Shift
The balanced spool assemblies shift to the dis-
pense position
Material path to the mixer inlet is opened
Material feed inlet ports (A,B) are blocked
Metering rods (E) remain in the retracted position
18
Step 3: Dispense
Metering rods (E) extend
A and B materials are simultaneously dispensed
from the metering chamber into the disposable
mixer
A and B materials are dispensed at the predeter-
mined volume ratio.
Upon completion of the dispense stroke, the metering
rod (E) and spool assemblies shift back to the reload
position.
3A7284B