This is the installation and registration guide for CET Meter which is referred to as MB-63 or 6M+One device on our system. Throughout the rest of the document, the device will be addressed as CET Meter Installation guide (Link for the SLDs: https://drive.google.com/drive/folders/1SK--jg-cPQgHH2JOm3B7fxpZGIdwI27G) 1.
Page 2
4. PMC-220 ○ Hardware installation Straight through connection MB-63 Modbus D (+) and D (-) (NOT ) are to be connected to Terminal 7 ▽ and 8 respectively. ○ Configuration Making sure the device has the correct ID ↵ 2s, ↓ x1, PW, ↵ x1, enter the password as 0000 to enter the configuration mode, then press ↓...
Page 3
↓ until you see the CoM SET, make sure the ID is set to 100. 7. Final check — voltage test! Solar Analytics is unable to do a remote phase-swap with the CET Meter, hence, the installation has to be correct on the spot! ○...