HP POD 40c G2 structure
Component to be inspected
Complete structure
—
—
Life safety
Component to be inspected
EPO system
—
—
—
—
—
—
—
Security
Component to be inspected
System functional test
—
Task
Visually inspect the structural
integrity.
Inspect the door operation and
inspect the door gaskets for water
and air leaks.
Visually inspect the paint. Perform
prep and touch-up as necessary.
Task
EPO functional test with manual
and automatic shutdown. (Verify
all shunt-trips on all panels trip.)
EPO alarms
EPO bypass keyed switch
(functional test)
EPO bypass switch located at
each personnel door. (Functional
test. Verify system time-out reset
when switch is activated.)
EPO status light. (Verify operation
in different modes. Replace lamps
as necessary.)
Exit lights. (Verify exit lights are
visible when all lighting is off and
POD doors are closed.)
Tritium exit signs (Visual
inspection)
Personnel door emergency egress
panic bars. (Visual and
operational inspection.)
Task
Visual inspection and operational
test of door access contact
switches
Visual inspection and operational
test of door access card readers,
electric strikes, and door release
switches at each personnel door
and/or in each personnel door
panic bar
Frequency
Capable Party
Annually
Certified facilities
personnel
Annually
Certified facilities
personnel
Annually
Certified facilities
personnel
Frequency
Capable Party
Annually
Licensed EPO safety
contractor
Annually
Licensed EPO safety
contractor
Annually
Licensed EPO safety
contractor
Annually
Licensed EPO safety
contractor
Annually
Licensed EPO safety
contractor
Bi-annually
Certified facilities
personnel
Bi-annually
Certified facilities
personnel
Bi-annually
Certified facilities
personnel
Frequency
Capable Party
Annually
Certified facilities
personnel
Annually
Certified facilities
personnel
Periodic maintenance 68