HP POD 40c G2 Maintenance And Service Manual page 66

Performance optimized datacenter
Table of Contents

Advertisement

Component to be inspected
Task
Electrical panel, breaker,
disconnect, and transformer visual
inspection for condensation or
other degradation of buses and
connections
Electrical panel, breaker,
disconnect, and transformer bolt
torque testing. Retighten as
necessary.
Grounding system resistance test
Ground and grounding
connection/lug located internal of
each electrical panel torque test.
Clean and retighten as necessary.
Grounding connection/lug
located external on the POD
torque test. Clean and retighten as
necessary.
Service entrance ground
connection/lug located at external
transformer and switchboard
torque test. Clean and retighten as
necessary.
Service entrance grounding
ground-rod/ground well
connecting/lug located at
locations external to POD torque
test. Clean and retighten as
necessary.
Grounding system bonding
jumpers connecting racks to POD
structure and rack to rack torque
test. Clean and retighten as
necessary.
Panel breaker operational test
(Simulate a breaker response to a
load greater than the breaker
rating.)
Visual inspection of breakers,
disconnects, motor starters, and
fuse holders
Calibrate all temperature,
pressure, and humidity sensors.
Visual inspection of lighting
fixtures and lamps. Measure foot
candles and replace as necessary.
Frequency
Capable Party
Annually
Licensed electrician
Annually
Licensed electrician
Bi-annually
Licensed electrician
Bi-annually
Licensed electrician
Bi-annually
Licensed electrician
Bi-annually
Licensed electrician
Bi-annually
Licensed electrician
Bi-annually
Licensed electrician
Annually
Licensed electrician
Bi-annually
Licensed
electrician/Certified
facilities personnel
Annually
Certified facilities
personnel
Bi-annually
Licensed
electrician/Certified
facilities personnel
Periodic maintenance 66