Connecting the system
Required equipment
PD-TaD incl. connection cables
HF filter
PoE cable
Laptop incl. Ethernet and USB cable
Anti-corona protection
Note:All the necessary connection cables and connecting elements are included in the
standard delivery.
Procedure
The illustration shows an example of a standalone system with a PHG portable VLF HV
generator and an HV connection cable with screen. The standalone system is connected to
a different VLF HV generator or an HV connection cable without screen in the same way.
Important:
 To keep the connection cable between the PD-TaD and the test object short, place the
PD-TaD as close as possible to the test object.
To avoid interference due to partial discharge at the connection point, make sure the PD-
TaD is placed a sufficient distance away from metal and live parts.
If the connection point is higher up, put the PD-TaD on a substructure. Further
information: Chapter Securing the PD-TaD 80 to the cross beam (on page 33)
 Keep all connections as short as possible.
 Lay out the connection cables in such a way that no loops are created.
The numbering in the table gives the sequence of steps for connecting the test object.