Preventative Maintenance Schedule

All Sentry Standard Series

Page 5-4

PM Intervals

PM Intervals are based on an average usage of a 16 hour production day.
FREQUENCY
12
96
192
5760
17,280
34,560
All general information about machine maintenance is based on normal machine working
conditions: indoor, moderate dust and low moisture environment, and maximum rotation
of 9 RPM. They should be regarded as guidelines, reviewed and corrected according to
requirements of actual use and conditions.

Daily

Prior to switching the film roll, inspect that there is no excess film wrapped around
any of the carriage rollers.
Use compressed air to blow out any loose debris in the carriage.
Monitor the machine during operation for any abnormal noises or vibrations.

5,760 Loads or one month

Inspect rubber stretch rollers. Clean as needed per instructions in manual. Replace
worn rollers, as needed.

17,280 Loads or three months

Inspect under turntable. Check the chain tensioner. Use compressed air to clean debris
as needed.
Inspect turntable support casters for good condition.
Inspect carriage lift chain condition. Tension as needed. Apply a light coating of lubri-
cant.
Inspect prestretch chain. Tension as needed. Apply a light coating of lubricant.
Inspect turntable chain. Tension as needed. Apply a light coating of lubricant.

34,560 Loads or 6 months.

Check all hardware. Tighten screws and bolts, as needed.
Table 5-2. PM Frequency
PERIOD
LPH
LPS
LPD
LPM
LP3M
LP6M
Orion
Revision 2.8
27 August 2014
DESCRIPTION
(Hour)
(Shift)
(Day)
(Month)
(3Months)
(6Months)

Advertisement

Table of Contents
loading

Table of Contents