machine in chiller and temperature/pressure inside the differential dF30: exchanger 1 and exchanger
2 ON
machine in heat pump and temperature/pressure inside the differential dF33: exchanger 2 ON
machine in heat pump and temperature/pressure inside the differential dF34: exchanger 1 and
exchanger 2 ON
In chiller when first compressor starts both exchangers are ON for dF36 time; after this time the regulation
follows diagrams above.
If dF36=0 the regulation follows diagrams above also at the start up.
In defrost this regulation is disabled.
In STD-BY or remote OFF the status of the exchangers is hybrid exchanger 1=ON, hybrid exchanger
2=OFF.
The set point is related to the status of the machine:
if the machine is producing cooled water and domestic hot water, reference set point is chiller set
point
if the machine is producing only domestic hot water, reference set point is heat pump set point
41. GEOTHERMAL FREE COOLING
Outputs managed:
relay for valve/pump management
0..10V analog output to control a modulating valve
In heating the relay is OFF and the analog output is 0V.
Free cooling operation mode:
CF77=2: Free cooling is the only cooling source
CF77=3: Free cooling and compressors work together to produce cooling. The compressors work
according their standard regulation.
Free cooling management:
2 probes are needed, selected from those configured in the instrument (1 Pb1, 2=Pb2, etc.); parameters to
select the probes are FS41 and FS42.
if T1 temperature – T2 temperature FS21, the Free cooling is enabled and the relay and analog
output are manages as figures below
if T1 temperature – T2 temperature < FS21 – FS22, the Free cooling is disabled
Analog output management: