Doosan Power Train D50S-5 Specifications Systems Operation Testing & Adjusting Disassembly & Assembly page 40

Hide thumbs Also See for Power Train D50S-5:
Table of Contents

Advertisement

Separation of Torque Converter and
Transmission from Engine
Start By:
a. Remove engine, torque converter and
transmission.
1
1. Remove bolts (1) and plate (2) from flywheel
housing.
2. Remove six bolts (3) that hold plate (4) to the
flywheel.
3. Move plate (4) and torque converter away from
the flywheel.
4. Separate transmission and torque converter (5)
from the engine.
Power Train
Connection of Torque Converter and
Transmission to Engine
1. Put the transmission and torque converter (5) into
position and make a connection of the
transmission and torque converter.
2. Move torque converter plate (4) toward flywheel
until plate (4) makes contact with the flywheel and
check if torque converter turns freely.
3. Install bolts (3) finger tight that hold plate (4) to
the flywheel.
4. Turn the flywheel in a counterclockwise direction
and tighten the bolts (3) to a torque of
........................................................ 19 ± 1 N•m
1
5. Put plate (2) in position and install bolts (1).
End By:
a. Install engine torque converter and transmission.
39
(14±1 lb•ft)
Disassembly and Assembly