6.1.4 Installation Plan and Support
It is recommended that a GE field representative review all installation/construction drawings and the cable and conduit
schedule when completed. This optional review service ensures that the drawings meet installation requirements and are
complete.
Optional installation support is offered: planning, practices, equipment placement, and onsite interpretation of construction
and equipment drawings. Engineering services are also offered to develop transition and implementation plans to install and
commission new equipment in both new and existing (revamp) facilities.
6.1.5 Customer's Conduit and Cable Schedule
The customer's finished conduit and cable schedule should include:
Interconnection wire list (optional)
Level definitions
Shield terminations
The cable and conduit schedule should define signal levels and classes of wiring (refer to the section,
Routing). This information should be listed in a separate column to help prevent installation errors.
The cable and conduit schedule should include the signal level definitions in the instructions. This provides all level
restriction and practice information needed before installing cables.
The conduit and cable schedule should indicate shield terminal practice for each shielded cable (refer to the section,
Connecting the
System).
Installation Guidelines
Public Information
Cable Separation and
GEH-6721_Vol_I_BP System Guide 129