6.1.2 GE Installation Documents
Installation documents consist of both general and requisition-specific information. The cycle time and the project size
determine the quantity and level of documentation provided to the customer.
General information, such as this document, provides product-specific guidelines for the equipment. They are intended as
supplements to the requisition-specific information.
Requisition documents, such as outline drawings and elementary diagrams provide data specific to a custom application.
Therefore, they reflect the customer's specific installation needs and should be used as the primary data source.
As-Shipped drawings consist primarily of elementary diagrams revised to incorporate any revisions or changes made during
manufacture and test. These are issued when the equipment is ready to ship. Revisions made after the equipment ships, but
before start of installation, are sent as Field Changes, with the changes circled and dated.
6.1.3 Technical Advisory Options
To assist the customer, GE offers the optional technical advisory services of field engineers for:
Review of customer's installation plan
Installation support
These services are not normally included as installation support or in basic startup and commissioning services displayed
below. GE presents installation support options to the customer during the contract negotiation phase.
128
GEH-6721_Vol_I_BP
Startup and Commissioning Services Cycle
GEH-6721_Vol_I Mark VIe and Mark VIeS Control Systems Volume I
Public Information