10.4 DOWNWARDS PUMPING
For downwards pumping, the horizontal section of pipe must be
aligned and supported with bags of cement or bricks. Use a wide
bend for the connection between the horizontal and downwards
sections. Use a solid support under the bend itself (Fig. 13 Ref. 1).
In the downwards section, the material flow must be decelerated
with a bend and opposing bend (Fig. 13 Ref. 2).
Fig. 13
11. The pump can also be used with the following accesso-
ries: standard remote control, remote control, Spritz Beton,
set accelerant pump and high pressure water cleaner.
11.1 STANDARD REMOTE CONTROL
The machine is equipped with a cabled remote (Fig. 14 Ref. 1)
which connects to the socket (Fig. 14 Ref. 2) on the machine's
chassis. When using the remote, the switch (Fig. 14 Ref. 3) on the
panel must be set to "LOC".
1
Fig. 14
11.2 OPTIONAL REMOTE CONTROL
The machine is equipped with a remote control (Fig. 15), which is
enabled by setting the switch (Fig. 14 Ref. 3) on the panel to REM.
If necessary, connected the remote (Fig. 14 Ref. 1) to the provided
socket (Fig. 14 Ref. 2).
11.3 SPRITZ BETON VERSION
When the machine is used for spraying concrete, use the 15mm
grill, the vibrator, the Spritz Beton jet and an auxiliary compressor.
Connect the delivery pipe to the jet (Fig. 16 Ref. 1) and the air
delivery pipe to the intake (Fig. 16 Ref. 2)
IMER INTERNATIONAL S.p.A.
2
1
2
4
3
Fig. 15
1
Fig. 16
11.4 SET ACCELERANT PUMP
-Caution! Set accelerants are aggressive for the eyes and skin. Use
appropriate protective equipment - gloves and face mask: always handle
this material with the greatest care and following the manufacturer' s
instructions to the letter.
When using the accelerant pump, connect the material intake pipe
to the quick release (Fig. 17 Ref. 1), and the other end of the pipe
to the tank containing the accelerant itself.
Check that the accelerant tank suction fitting is at least 50cm
above the connector (Fig. 17 Ref. 1).
The accelerant delivery pipe must be connected to the quick
release (Fig. 17 Ref. 2) on the machine and the jet's quick release
fitting (Fig. 17 Ref. 3).
- Only use original IMER pipes and fittings. The use of pipes and
fittings not complying with IMER specifications can compromise
correct machine operation as well as the safety of operators.
- Before starting work, always check that the pipes, fittings and
gaskets are in perfect condition.