Install the System in the Rack.
7. Check the PSNT label at the rear of the chassis.
Figure 27 Location of serial number tag
Repeat these steps to install the second node.

Mount the cable management assembly on both nodes

A cable management assembly (CMA), for organization of cables at the rear of the
system, is already installed onto the DD9500 system on an EMC rack.
For field installed systems, the CMA is shipped separately.
Note
For non-EMC racks, it is acceptable to use the cable management products provided by
the rack vendor.
Mount the cable management assembly on both nodes
41

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Data Domain DD9500 System and is the answer not in the manual?

Questions and answers

Related Products for EMC2 Data Domain DD9500 System

Table of Contents