Electrical installation
Figure 4-3
Connection
When connecting the dv/dt reactor and Voltage Peak Limiter, you must take into account the
following conditions to ensure that it functions correctly:
● Control cables must be routed separately from power cables. Power cables are the motor
cable or the connecting cables from the DC link of the Power Module (terminals
DCPS/DCNS) to the Voltage Peak Limiter. In particular, you must ensure that control
cables and power cables are not routed in parallel in a joint cable raceway, even if all the
cables are shielded.
● It is recommended to use shielded motor cables. If a shielded motor cable is used, its
shield should be in face-to-face contact with the shield plate and motor housing.
● The ground wire for the motor must be fed directly back to the Power Module.