Periodic maintenance
Periodic maintenance overview
Perform periodic inspections on the components in this section to ensure that the HP POD 40c NA continues
to perform within the designed parameters.
Qualified personnel
Qualified personnel are identified as personnel who are:
•
Properly trained in the operation and maintenance of the HP POD 40c NA
•
Customer-authorized to conduct maintenance activities
Qualified personnel can be:
•
HP personnel
•
Agents for HP
•
Site maintenance personnel
Cooling system maintenance schedule
Component to be inspected
Air filters
Air filter differential pressure
sensor
Cooling system leak check
Condensate drain pans
Condensate drain pan sensors
Task
Inspect and replace as necessary
Inspect and test, replace as
necessary
Verify there is no visible chilled
water leak from:
•
Heat exchanger
•
Cold water supply piping
•
Cold water return piping
If a leak is detected, see "Leak
detection maintenance (on page
63)"
Inspect pans:
•
Free of debris
•
No leaks
•
Leakage detectors are in
proper position
Clean pans as necessary
Inspect and test, replace as
necessary
If a leak is detected, see "Leak
detection maintenance (on page
63)"
Frequency
Capable Party
Quarterly, or as
Qualified personnel
needed
Annually
Qualified personnel
Quarterly
Qualified personnel
Quarterly
Qualified personnel
Quarterly
Qualified personnel
Periodic maintenance 62