Connections

1. The A2--A6 Process Controller is to be connected by a qualified person.
2. For the connection of A6 GMD, see instruction manual 0443 403 xxx.
3. For the connection of A6 PAK, see instruction manual 0443 405 xxx.
4. Connect the welding head as follows:
The control cable (7) between the welding power source (8) and the A2--A6
S
Process Controller (2).
The return cable (11) between the welding power source (8) and the
S
workpiece (9).
The welding cable (10) between the welding power source (8) and the
S
welding head (1).
The gas hose (5) between the pressure reducing valve (6) and the gas valve
S
of the welding head (13).
The hoses for cooling water (3) between the cooling unit (4) and the welding
S
head (1).
The measuring cable (12) between the welding power source (8) and the
S
workpiece (9).