FIGURE 3 – AC LINE AND ARMATURE CONNECTION
6.3 Fusing
AC Line Fuse – The KBRG-212D does not contain an AC line fuse or
fuse. It is recommended that a 20 Amp fuse or circuit breaker be
each AC line conductor not at ground potential. In addition, refer to Table
recommended Armature Fusing.
CAUTION: Most electrical codes require that each ungrounded conductor contain
fusing. Separate branch circuit fusing may be required. Check local electrical codes.
6.4
Motor Armature – Connect motor armature to terminals M1 and M2. Be sure that
jumper J2 matches the motor being used. (See Figure 3).
Motor Horsepower
90 VDC
1/8
1/6
¼
1/3
½
¾
1
6.5
Field (For Shunt Wound Motors Only) – Connect motor armature leads as above.
Connect full voltage shunt field leads (90 volt motors with 100 volt fields and 180 volt
with 200 volt fields) to F+ and F-. Connect half voltage field leads (90 volt motors
with 50 volt fields and 180 volt motors with 100 volt fields) to F+ and L1. See Table
8, Figures 4 and 5, on page 15, for field connection diagrams.
CAUTION! Shunt-Wound motors may be damaged if field remains connected without
motor rotating for an extended period of time.
Note: Do not connect motor armature leads to F+ and F- terminals. Do not use F+ and F-
terminals for PM motors.
14
TB2
L1
L2
M2 M1
GND
(EARTH)
AC LINE
ARMATURE
INPUT
See Table 6, for Torque Requirements.
TABLE 7 – ARMATURE FUSE CHART
180 VDC
¼
1/3
½
¾
1
½
1
2
TB3
F+
F-
+
M
-
Approx. DC Motor
Current Amps
1.3
1.7
2.5
3.3
5.0
7.5
10.0
Armature
installed on
7,
for
Fuse Rating
(AC Amps)
2
½
2
4
5
8
12
20

Hide quick links:

Advertisement

Table of Contents
loading