29. Installation Checkpoints

a) Before Starting The Boiler: Do not turn on the boiler unless it is filled with water as shown
by indicating light on panel box.
b) Check that the front door of the air decoupler box is closed. Door must be closed before
starting the boiler. Do not open during operation.
c) Set the temperature control to the desired setting.
d) Open the manual shut off gas valve.
e) Close the circuit breaker or the fuse disconnect.
f)
Turn the on-off switch to "ON"
Fulton Heating Solutions, Inc. -- PHW Manual -- 2010-0713
11. Make sure the following are closed--all drain cocks, the vent on the
combination shutoff-purge valve, and all manual vents. Reset zone
valves to normal mode of operation and turn off power to boiler.
12. Open gas shutoff valve, allowing gas to flow to boiler.