Commissioning

I
NTRODUCTION
F
S
ACTORY
ETTINGS
A
DJUSTMENT
Step 1:
Preparation
This section describes how to start up and adjust the
Eclipse Linnox burners.
Danger:
The burners covered by this Guide are designed to
mix gas with air and burn the resulting mixture.
All gas burning devices are capable of producing
fires and explosions if improperly applied, installed,
adjusted, controlled or maintained.
Do not bypass any safety feature! Fire or explosion
could result.
Never try to light a burner if it shows signs of
damage or malfunction.
All pressure switches are factory adjusted.
The mixer gas nozzles are sized for the correct gas type.
Adjustment steps:
1. Preparation
2. Dry run
3. Combustion air check
4. Start-up and low fire adjustment
5. Operating checks
1. Ensure all installation work has been completed in
compliance with current legislated standards.
2. Ensure that all gas supply pipework has been purged of air in
compliance with current legislated standards.
3. Ensure that all required services are available.
4. Ensure that all pre-checks have been completed in
compliance with current legislated standards.
5. Ensure that the following instruments are available
- digital or "U"- tube manometer for pressure adjustments.
- µA - meter to measure flame signal strengths.
Eclipse Linnox Model CCS-LS, Installation Guide 159, 2/20/04