Step 10: Normal Operation (Post
Commissioning)
Start Procedure
1. Start the blower.
2. Open all the gas cocks.
3. Start the ignition sequence.
4. Verify that flame is present at each burner.
■ If a burner does not light, and the system does not
shut down automatically, then you must close the
main gas cock. An uncontrolled flow of gas can
cause fires and explosions.
■ Do not touch the ignition plug or the ignition wire
when the ignition is on. You will get a shock.
Stop Procedure
1. Close the following valves:
• The manual gas cock for each burner or zone
• The manual gas cock at the main control valve
• All the manual shut-off valves in the gas line
upstream of the burner gas cock
2. Let the burners cool down. Keep the blower on until
the chamber temperature is less than 1000°F (500°C)
and then stop the blower.
NOTE: Keeping the blower on after the burner is off
protects the burner and the components from hot gases
that flow back through the burner.
Eclipse ThermJet Self-Recuperative, V5, Installation Guide 208, 2/4/2013