Step 4:
Start-up
5. Verify high fire air
a. Drive control motor to high fire, fully open.
b. If high fire air is insufficient, refer to Section 7,
"Trouble-shooting".
6. Return the control motor to low fire position.
7. Close the pressure taps.
Start-up procedure:
1. Check the pre-setting of the adjustment valves.
2. Switch the control motor to "automatic".
3. Open the manual isolating ball valve.
4. Initiate the burner management system to start the operating
sequence. The control motor will be controlled to the start
position after which the ignition will take place.
The ignition support flame should appear approx. 2"-8" (5 - 20
cm) beyond the flame shields in a mixed blue and yellow colour.
If flame is too weak or too big, adjust the support flame with
adjusting valve (7). Support flame appearance also depends on
the start position of the combustion air valve.
After the pre-ignition time (2 sec. according EN 746-2) the 2nd
shut-off valve will open and the Linnox burner will be ignited. A
clear blue line flame will appear at the burner base. The appear-
ance will vary for the different capacity ratings of the burner
elements.
If the burner does not light the first time it will be necessary to
reset the burner programmer and follow this procedure again.
5. If the the burner did not ignite:
a. Attempt to ignite the burner again after purging air
from the gas piping.
b. If the support flame does not appear, open the
adjusting valve (11) 1 turn.
c. If the flame appears at ignition, but the main burner does
not light, turn the bias adjusting screw of the gas ratio
regulator (5) one turn clockwise to increase gas flow and
try to ignite the burner again.
d. Repeat steps b and c until burner ignites. If the burner
does not ignite, follow guidelines in Section 7 "Trouble-
shooting".
Eclipse Linnox Model CCS-LS, Installation Guide 159, 2/20/04