8.6.2

Preparation of the AC port for the building grid

Figure 11: Stripping cables

To connect to the building grid, the 5-wire AC cable must be
connected to the supplied AC connector.
Strip the cable 40 mm at the end.
The PE conductor must be 5 mm longer than the other
four conductors (L1, L2, L3, N). Shorten these conductors
accordingly.
i
Strip the wires for the building connection approx. 8 mm at
the ends.
Ferrules must be used for fine-stranded conductors.
Screw off the union nut of the strain relief.
Take off the connector housing: To do so, release the
catch by pressing on the two side lugs at the same time.
Push union nut and connector housing over the cable.
Subject to modification!
A flexible plastic-sheathed cable facilitates
assembly work.
Updated 10/2017
71

Advertisement

Table of Contents
loading

Related Products for Varta element Series

This manual is also suitable for:

Element 6Element 9Element 12Element 3

Table of Contents