Flues And Ventilation; Installation Notes; Ventilation - Trianco Contractor WM70 HE INTERNAL User, Installation, Commissioning & Servicing Instructions

Oil-fired central heating boiler for balanced flue
Table of Contents

Advertisement

8. FLUES AND VENTILATION

VENTILATION

As the Contractor WM70 HE is a balanced-flue appliance, the
provision of an adequate supply of combustion air is not
necessary. However, adequate ventilation is required for the
cooling of the boiler controls if the appliance is to be installed in
a compartment or confined space (see fig 19).
The air opening should be positioned so as to cause the least
possible draught to the occupants and located so it is not liable
to be accidentally blocked.
British Code of Practice BS 5410: Part 1 requires a permanent
air inlet opening of 550mm
above 5kW.
The following air openings, shown on fig 19, are required for
the Contractor WM70 HE.
Output
50,000 Btu/h
60,000 Btu/h
70,000 Btu/h
VENTILATION
2
per kW of boiler rated output
Detail 'A' (fig 19)
53cm²
69cm²
83cm²
FIG 19
18

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Contractor WM70 HE INTERNAL and is the answer not in the manual?

Table of Contents