Figure 6 Piping Connections For Water/Glycol And Glycool Units - Emerson Liebert Challenger 3000 Installation Manual

Precision cooling for business-critical continuity, 3 & 5 tons, 50 & 60hz
Hide thumbs Also See for Liebert Challenger 3000:
Table of Contents

Advertisement

Figure 6
Piping connections for water/glycol and GLYCOOL units
DOWNFLOW (BF, BE) MODELS
Condensate Drain 3/4" FPT
Field pitch a min. of 1/8" (3.2mm) per ft. (305mm).
The drain line must comply
with all applicable codes.
Humi d ifier Water Supply Line
1/4" OD CU
PIPING OUTLET LOCATIONS
(See Cabinet and Floor Planning
Dimensional Data for Piping Opening Sizes.)
Monitoring Panel
Condenser S upply Line
7/8" OD CU on Models BF046WG/BF045WG
1 1/8" OD CU on Models BF071WG/BF070WG
Condenser Re turn Line
7/8" OD CU on Models BF046WG/BF045WG
1 1/8" OD CU on Models BF071WG/BF070WG
Hot Water Return
5/8" OD CU (optional)
Hot Water Suppl y
5/8" OD CU (optional)
9
Installation
SL-11898 PG 10

Advertisement

Table of Contents
loading

Table of Contents