Commissioning

6.1 Commissioning the Sunny String-Monitor
The commissioning report must be filled out during commissioning. The commissioning report form is
enclosed with the Sunny Central.
Requirements:
☐ The DC circuit breaker is disconnected.
☐ The DC main cables are connected to the inverter or DC distribution box and are activated.
There is no reverse voltage from the inverter.
☐ All connections are made according to this manual (see chapter 5 "Electrical
Connection", page 20).
Check the following points and document them in the commissioning report:
• Polarity of the DC voltages at the string inputs and at the DC main cables.
• All strings have similar voltage values.
• Check for the absence of ground faults on the strings and the DC main cables.
• Inspect the screw connections visually.
• Fuses correspond to the system design.
• The terminal allocation of the data cable is correct.
• All covers have been replaced.