7.
After the cable connection is complete in the wiring cavity, tighten the screws on the
cover to close the wiring cavity using M4 cross screwdriver.

3.6.6 Connect Ground Cable

Make the grounding cable according the actual situation of the installation site.
The Nova-243 provides two grounding screws, which is located on the bottom of the
base station, as shown in Figure 3-4.
1.
Unscrew one grounding screw, connect one end of the grounding cable to the
grounding screw, and fasten it again.
2.
The other end of the ground cable needs to connect to a good grounding point.
The connection point can be done with rust preventing paint, anti-oxidation coatings,
grease, etc.

Figure 3-4 Location of Grounding Screws