4.
Drill three 12mm diameter holes in the wall on the marked locations, and
insert the expansion pipes.
5.
Fix base station to the wall with M8 x 80 expansion bolts.
3.6

Connect Cable

3.6.1 Requirement for Cable Laying

General requirements:
Bending radius requirement of feeder cable: 7/8" > 250mm, 4/5" > 380mm.
Bending radius requirement of jumper cable: 1/4" > 35mm, 1/2" (super soft) > 50mm,
1/2" (ordinary)>127mm.
Bending radius requirement of power cable and grounding cable: > tripled of the
diameter of cable.
Binding the cables according the type of the cable, the intertwining and crossing is
forbidden.
The label should be paste after the cable laying.
Grounding laying requirement:
The grounding cable must connect to the grounding point.
The grounding cable must be separate with the signal cables, remaining a certain
distance to avoid the interruption of signal.