6.2
Parameterizing/configuring
6.2.1
Commissioning
NOTICE
Since the commissioning and parameterization of the speed monitor are important safety-
related steps, they must be carried out by qualified personnel.
Requirements
The following requirements must be met for commissioning:
● The device has been installed
For more information see: Chapter "Assembling (Page 29)"
● Check all the latches to ensure that they are properly engaged.
● The device has been wired
For more information see: Chapter "Connecting (Page 33)"
● The parameterization is available and consistent.
● The power supply for the device is connected.
3TK2810-1 safety-related speed monitor
System Manual, 01/2011, 926246402000 DS 02
Operation
6.2 Parameterizing/configuring
41