3-5-9. REPLACEMENT OF THE REEL
UNIT
1.
Remove 6 screws (L) and carefully lift the DD Reel
Unit.
2.
Disconnect a connector.
SCREWS (L)
CONNECTOR
Figure M18-A
3.
The Reel Motor Unit can be re-installed by
reversing the removal procedure.
MAIN ROD
~
CUT WASHERS
Figure M18-B
Note:
When assembling the DD Reel Motor Unit,
side the Main Rod to far left side by rotating
a center Gear.
3-5-10.
REPLACEMENT OF THE MAIN
BRAKE (S),(T) UNIT
1.
Remove the Reel Unit (Refer to Replacement of
the Reel Unit).
2.
Remove a Retaining Ring (A).
3.
Remove the Main Brake (S),(T) with a spring.
RETAINING RING (A)
BRAKE SOLENOID
Figure M 19
4.
The new Main
Brake (S),(T) Unit can
be
reinstalled by reversing the removal procedure.
Note:
When assembling the DD Reel Motor Unit,
slide the Main Rod to far left side by rotating
a Center Gear (Figure M19).
3-5-11.
REPLACEMENT OF THE
PRESSURE ROLLER UNIT
1.
Place the deck in or EJECT mode.
2.
Remove the Pinch Can Cap.
3.
Remove the Pressure Roller Unit.
PINCH CAM GAP
PRESSURE ROLLER UNIT
Figure M20
4.
The new Pressure Roller Unit can be re-installed
by reversing the removal procedure.
3-13