Wrap Up Checklist

Once you have completed the installation the system is ready to be placed in service. Prior to placing the system in ser-
vice review the following checklist to be sure the system is properly installed.
Check List
‰ The media tank(s) has been properly loaded with gravel and media.
‰ Retighten the nuts on all hand-hole covers, if applicable. The drain line has been properly installed.
‰ All option kits have been properly installed.
‰ The system has been properly piped and tubed.
‰ Air has been bled from the MVP controller pilot valve tubing and the system has been properly pressurized.
‰ Each media tank has been backwashed manually.
‰ The MVP controller(s) have been correctly and completely wired, including differential pressure switches if
equipped.
‰ All MVP controllers have been properly programmed and are active (power on).
‰ All manual isolation valves are open and system by-pass valves are closed.
‰ Clean up the unit and the installation site, removing any soldering or pipe threading residues from the equipment
with a damp towel.
‰ For units with steel tanks, place the Culligan label (packed with the media tank) on the front of the tank.
‰ Explain the operation of the system and the Suggested Preventative Maintenance Inspection Schedule
49) to the customer.