INSTALLATION

2.3 Installation premises

The Condexa PRO NA can be installed in rooms that are perma-
nently ventilated and equipped with suitably sized ventilation
openings in line with Technical Standards and Regulations appli-
cable to the installation site.
9
WARNING: When installing the boiler, allow sufficient space
around it to access all safety and control devices and to permit
easy maintenance.
9
WARNING: Check that the electric protection level of the appli-
ance is suitable for features of the room where it is installed.
9
WARNING: Make sure that comburent air is not contaminat-
ed by substances containing chlorine or fluorine (elements
found in sprays, paints, detergents etc.).
0
WARNING: Do not obstruct or restrict the air vents in the room
where the boiler is installed. A free air supply is essential for
correct combustion.
0
WARNING: It is forbidden to leave flammable containers and
substances in the room where the boiler is installed.

2.3.1 Installation clearances

Recommended minimum clearances for installation and servicing
(dimensions in inches [mm]).
The minimum surface of ventilation openings is 3.2ft
gas fuel heating systems.
2.4 Installation in older systems and systems
requiring modifications
When installing these boilers in older systems or systems requiring
modifications, always perform the following checks:
− Make sure that the flue is able to withstand the tempera-
ture of the combustion gases and that it has been designed
and made in compliance with applicable standards. The
flue must also be as straight as possible, sealed, insulated
and not blocked or choked. See section "Combustion gas
exhaust" for any additional information.
− Make sure that the electrical supply system has been in-
stalled by a qualified electrician in compliance with appli-
cable standards
− Make sure that the fuel feed line and any storage tank are
made and installed in compliance with applicable stan-
dards
− Make sure that expansion tank(s) are big enough to contain
the additional volume generated by thermal expansion
− Make sure that the flow rate, head and direction of flow of
the pumps are suitable and correct
− The system has been washed, cleaned of mud and grime
and water seals have been checked
− A treatment system is fitted when the supply/refill water
has values other than those indicated in Paragraph "Water
Chemistry Guidelines"
9
NOTE: The manufacturer declines all responsibility for damage
caused by incorrectly constructed flue systems.

2.5 Moving and removing the packaging

9
NOTE: Do not remove the cardboard packaging until your reach
the installation location.
9
Before handling the appliance and removing the packaging,
wear personal protective equipment (PPE) and use tools suit-
able for the appliance's size and weight.
9
This step must be carried out by several individuals equipped
with suitable means with respect to the appliance's size.
Make sure that the load is not unbalanced during handling.
Proceed as follows to remove the packing:
− Remove the strapping that secures the cardboard packag-
ing to the pallet
− Remove the cardboard
− Remove edge protectors (1)
− Remove the Styrofoam protection (2)
− Remove the protective bag (3)
3
1
2
(0.3m
2
) for
16
2
1
1