Installing Interface Connections; Installing Building Alarm Connections; Figure 4-8 Interface Terminal Locations - Eaton 9EHD-33-40/20 User's Installation And Operation Manual

20-40 kva (380/400/415v)
Table of Contents

Advertisement

4 5

Installing Interface Connections

4 5 1 Installing Building alarm Connections

To install wiring:
1.
Verify the UPS system is turned off and all power sources are removed. See Chapter 6, "UPS Operating
Instructions", for shutdown instructions.
2.
To locate the appropriate terminals and review the wiring and termination requirements, see
paragraph 3.2.3, Table 4-1, Figure 4-8 and Figure 4-12.
3.
Interface cables can enter the UPS via bottom hole see Figure4-8 and Figure4-13.
4.
Connect the building alarm interface wiring as shown in Table 4-1 and Figure 4-12.
5.
If wiring parallel connections, proceed to paragraph 4.5.2; if wiring Mini-Slot connections, proceed to
paragraph 4.5.3;
Interface Terminal
See Figure 4-9 for detail

figure 4-8 Interface Terminal locations

Eaton 9EHD UPS (20-40 kVA, 380/400/415V) Installation and Operation Manual
RS232
PAR IN/RJ45-1
PAR OUT/RJ45-2
Wiring Access
29