Integrated Transformer Cabinet Installation ..........Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1...
Page 6
6.3.10 Using the UPS LOAD OFF Command ..........6-15 Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Page 7
WARRANTY....................Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1...
Page 8
Table of Contents This page intentionally left blank. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Page 9
Air Filter Location ..............Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1...
List of Figures This page intentionally left blank. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Page 11
Input/Output Ratings and External Wiring Requirements for the Eaton 9E–20, 9E–30/20, and 9E–30/30 . . Table 3-6. UPS External Power Cable Terminations for the Eaton 9E–20, 9E–30/20, and 9E–30/30....Table 3-7.
List of Tables This page intentionally left blank. viii Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
AC power to protect the customer's load from power failures. The Eaton 9E 20–30 kVA online power protection system is used to prevent loss of valuable electronic information, minimize equipment downtime, and minimize the adverse effect on production equipment due to unexpected power problems.
The 9E–30/20 and 9E–30/30 UPS battery systems use internal batteries with External Battery Cabinet (EBC) capability. Up to two Eaton 9E External Battery Cabinets (EBCs) can be added to UPS system. The EBCs are connected in parallel with the internal batteries to provide extended run time.
External Battery Cabinet Capability EBC capability provides the ability to add Eaton 9E EBCs to the UPS system in addition to the internal batteries. An internal UPS battery breaker and external battery terminal block are added, along with other internal parts allowing the connection of up to two EBCs.
Reduced Battery String Model The Eaton 9E–20 model is configured with four battery strings instead of six to optimize the run time for 20 kVA with a subsequent reduction in cost and weight. Reduced battery string models are non-EBC capable. If increased battery run time is required in the future, an extended run battery upgrade kit is available to increase the internal battery system to six strings.
Introduction Using This Manual This manual describes how to install and operate the Eaton 9E 20–30 kVA. Read and understand the procedures described in this manual to ensure trouble-free installation and operation. In particular, be thoroughly familiar with the REPO procedure (see paragraph 6.3.11).
Installation instructions, including site preparation, planning for installation, wiring and safety information, and detailed illustrations of cabinets with dimensional and connection point drawings Refer to the Eaton 9E Integrated Accessory Cabinet-Tie and Bypass Installation and Operation Manual for the following additional information:...
Replace batteries with the same number and type of batteries as originally installed with the UPS. Disconnect the charging source prior to connecting or disconnecting terminals. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Page 20
Une mise au rebut réglementaire des batteries est obligatoire. Consulter les règlements en vigueur dans votre localité. Ne jamais jeter les batteries au feu. L'exposition aux flammes risque de les faire exploser. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
W-1 become void. This service is offered as part of the sales contract for the UPS. Contact an Eaton service representative in advance (usually a two-week notice is required) to reserve a preferred startup date.
From Right Side of Cabinet None Required From Left Side of Cabinet None Required Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
UPS Installation Plan and Unpacking Back Dimensions are in millimeters [inches] Front Right Side Figure 3-1. UPS Cabinet Dimensions (Front and Right Side Views) Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
UPS Installation Plan and Unpacking Front Front Bottom Dimensions are in millimeters [inches] Figure 3-2. UPS Cabinet Dimensions (Top and Bottom Views) Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Integrated Accessory Cabinet-Tie (IAC-T) or Integrated Accessory Cabinet-Tie and Bypass (IAC-TB) are the same as listed in Table 3-5. Refer to the Eaton 9E Integrated Accessory Cabinet-Tie and Bypass Installation and Operation Manual listed in paragraph 1.7 for additional IAC-T or IAC-TB wiring and termination requirements.
The number of neutral conductors listed are for single size neutral wiring. A 1.5x sized neutral can be supported by this product. Two terminal landings are provided to accommodate extra neutral wiring. Table 3-5. Input/Output Ratings and External Wiring Requirements for the Eaton 9E–20, 9E–30/20, and 9E–30/30 Units Rating 50/60 Hz...
The power wiring terminals are pressure terminations, UL and CSA rated at 90°C. See Table 3-6 for external power cable terminations. Figure 4-7 and Figure 4-8 show the location of the UPS power cable terminals. Table 3-6. UPS External Power Cable Terminations for the Eaton 9E–20, 9E–30/20, and 9E–30/30 Number and Size of Pressure Termination...
To reduce the risk of fire, connect only to a circuit provided with maximum input circuit breaker current ratings from Table 3-8 in accordance with the NEC, ANSI/NFPA 70. 3-10 Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
All control wiring and switch contacts are customer-supplied. LAN and telephone drops for use with Mini-Slot connectivity cards must be supplied by the customer. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality 3-11...
Carefully inspect the outer packaging for evidence of damage during transit. CAUTION Do not install a damaged cabinet. Report any damage to the carrier and contact an Eaton service representative immediately. NOTE For the following step, verify that the forklift or pallet jack is rated to handle the weight of the cabinet (see Table 3-3 for cabinet weight).
Page 35
Inspect the contents for any evidence of physical damage, and compare each item with the Bill of Lading. If damage has occurred or shortages are evident, contact an Eaton service representative immediately to determine the extent of the damage and its impact on further installation.
Attach the ramp extension to the front of the ramp by inserting the tabs on the extension into the slots at the bottom of the ramp. If the leveling feet are not fully retracted, turn the leveling feet until they are retracted. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Secure the UPS cabinet in position by lowering the leveling feet until the cabinet is not resting on the casters and the cabinet is level. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
UPS System Installation Figure 4-4. Rolling the Cabinet Down the Ramp Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Conduit Landing for AC Input, Output, and Bypass, DC Input, and REPO. Wire Hooks (Install conduit to bottom of plate.) Base (Inside View) Figure 4-5. UPS Power Terminal Cover Parts Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
(IAC-D); otherwise, proceed to paragraph 4.10 to complete the wiring of the UPS. Integrated Transformer Cabinet Installation If installing an ITC, refer to the Eaton 9E Integrated Transformer Cabinet Installation Manual listed in paragraph 1.7 for installation instructions. After the ITC is installed, proceed to paragraph 4.6 if installing an Sidecar Integrated Accessory Cabinet-Bypass (SIAC-B), to paragraph 4.7 if installing an IAC-B, or to paragraph 4.9 if installing an IAC-D;...
4.10 to complete the wiring of the UPS. Integrated Accessory Cabinet-Tie If installing an IAC-T, refer to the Eaton 9E Integrated Accessory Cabinet-Tie and Bypass Installation and Operation Manual listed in paragraph 1.7 for installation instructions.
AC Input to UPS Rectifier (A, B, C, N) (A, B, C, N) (Optional) (See Figure 4-8 for detail) (See Figure 4-8 for detail) Figure 4-7. Power Terminal Locations Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Phase C (L3) AC Input to UPS Rectifier Phase C (L3) Phase B (L2) UPS Bypass Neutral (N) Phase A (L1) Figure 4-8. Power Terminal Detail 4-10 Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Power Terminal Cover Right Side Installed Power Terminal Cover Power Terminal Cover Top Installed Left Side Installed Back Figure 4-9. Power Terminal Cover Top Installation Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality 4-11...
Mini-Slot Communication Bays Interface Terminals (See Figure 4-11 for detail) (See Figure 4-11 for detail) Top Rear Panel Back Figure 4-10. Interface Terminal Locations 4-12 Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
If not already removed, remove the power terminal cover top. Retain the cover top and hardware for later use. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality 4-13...
Page 50
Install the power terminal cover top using the provided hardware (see Figure 4-9). Install the power terminal cover right and left sides using the provided hardware. Proceed to paragraph 4.13. 4-14 Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Reinstall the top rear panel by tilting into position and securing the panel using the retained hardware. Reinstall the power terminal cover top using the retained hardware. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
NOTE LAN drop for use with Mini-Slot cards must be provided by the customer. For installation and setup of an Mini-Slot card, contact an Eaton service representative (see paragraph 1.7) To install wiring: If not already installed, install the LAN drop.
Page 55
UPS System Installation Figure 4-17. Parallel UPS Control Wiring Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality 4-19...
Connect the wiring as shown in Table 4-4 and Figure 4-20 for a normally-open REPO or Table 4-5 and Figure 4-21 for a normally-closed REPO. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Back of UPS Cabinet Wire Size Tightening Torque 3 NO Twisted Wires (2) 7 lb in 1422 AWG (0.8 Nm) 4 NO (0.754.0 mm 4-22 Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Connect the black connectors (see Figure 4-24) for each set of batteries on the battery shelf. Connect the red connectors (see Figure 4-24) for each set of batteries on the battery shelf. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Reinstall the internal safety shield panel removed in Step 2. Close the outside door and secure the latch. Bottom Internal Safety Shield Panel (Batteries are located behind safety shield.) Figure 4-22. Battery Location 4-24 Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Battery Shelf Battery Section Battery Strings NOTE The Eaton 9E–20 model has battery strings installed on two shelves. The Eaton 9E–30/20 and Eaton 9E–30/30 models have battery strings installed on three shelves. Figure 4-23. Battery Section Red Connector Black Connector...
Eaton Customer Service Engineer, or the warranty terms specified on page W-1 become void. This service is offered as part of the sales contract for the UPS. Contact an Eaton service representative in advance (usually a two-week notice is required) to reserve a preferred startup date.
Page 63
Accessories are mounted in installed locations and wiring is terminated inside the UPS cabinet. (Optional) Air conditioning equipment is installed and operating correctly. The area around the installed UPS system is clean and dust-free. (Eaton recommends that the UPS be installed on a level floor suitable for computer or electronic equipment.) Adequate workspace exists around the UPS and other cabinets.
Page 64
UPS System Installation Notes 4-28 Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Understanding UPS Operation UPS System Overview The Eaton 9E UPS is a continuous-duty, solid-state, transformerless, three-phase, true online system that provides conditioned and uninterruptible AC power to the UPS system's output and critical load. The basic system consists of a rectifier, battery converter, inverter, monitoring/operation control panel, integrated communication server, and digital signal processor (DSP) logic.
If the utility AC power is interrupted or is out of specification, the UPS automatically switches to Battery mode to support the critical load without interruption. When utility power returns, the UPS returns to Normal mode. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
If the UPS suffers an internal failure, it switches automatically to Bypass mode and remains in that mode until the failure is corrected and the UPS is back in service. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Main Power Flow Battery Breakers Switchgear Switchgear Trickle Current Closed Energized Open De-Energized Battery Figure 5-3. Path of Current Through the UPS in Bypass Mode Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Normal mode. Depending on the total load and the duration of the battery discharge, battery current limit alarms may be seen for a short time due to the current required to recharge the battery. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
See Figure 5-6 208/220 208/220 9E–30/30 External Battery Capable 9E–30/20 Single Reverse Transfer UPS with Internal and External See Figure 5-7 208/220 208/220 9E–30/30 Batteries Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
(Not supplied with the UPS) NOTE Callout letters A, B, C, and D map to Table 3-5. Figure 5-7. UPS System Oneline – Internal and External Batteries Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Figure 6-1 shows the controls and indicators and Figure 6-2 shows the UPS breakers. Control Panel Door Latch Figure 6-1. UPS Controls and Indicators Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Battery Circuit Breaker – The optional Battery circuit breaker is used to control the DC input to the UPS when the External Battery Cabinet (EBC) capable option is installed. This breaker disconnects both internal and external batteries. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
The following paragraphs describe using the UPS control panel to monitor the UPS. See paragraph 6.3 for use of the operational controls. When the unit powers up, the screen displays the Eaton logo as shown in Figure 6-3. To advance to the Main Menu and Mimic screen, press any control panel pushbutton once.
This message is also written to the Events Log and may be added to the History Log. The messages are divided into four categories: alarms, notices, status, and commands. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Figure 6-4. Parts of the LCD The UPS status area automatically scrolls between the Eaton model number, current date and time, active alarms, UPS status, load percent, and battery runtime for the UPS. The top line of display blinks while scrolling when the system needs attention.
Eaton Eaton 9E 9E 9E 9E Series Eaton Eaton Series Series UPS Series Figure 6-5. Main Menu and Mimic Screen Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
DOWN arrow pushbutton to highlight the desired format, then press the RETURN pushbutton to display the Set Date and Time screen. To return to the System Setup screen, press the ESC pushbutton. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Page 84
Once the password is entered, select CHANGE and then press the RETURN pushbutton Controls See paragraph 6.2.7 for details. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Table 6-5 lists the typical System Status Screen Messages that are displayed during UPS operation. For detailed information about using the System Controls, see paragraph 6.3. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
UPS Operating Instructions Single UPS Operation NOTE 1 If an External Battery Cabinet (EBC) is installed, refer to the Eaton 9E External Battery Cabinet Installation Manual listed in paragraph 1.7 for EBC battery breaker location. NOTE 2 If an Integrated Transformer Cabinet (ITC) is installed, refer to the Eaton 9E Integrated Transformer Cabinet Installation Manual listed in paragraph 1.7 for...
17 . If an ITC with an input and output transformer is installed, close the output breaker. The critical load is immediately supplied by the bypass source, in Bypass mode. 6-12 Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
On the UPS System Control screen, select the HE: ENABLE DISABLE command, then press the RETURN pushbutton. The UPS transfers to Standard Normal mode. The NORMAL status indicator is illuminated. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality 6-13...
Select the CONTROLS symbol on the main menu bar. The System Control screen is displayed. Select Battery on the System Control screen. On the Battery System Control screen, select the CHARGING RESTING command, then press the RETURN pushbutton. 6-14 Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
6.3.2. WARNING Power is present inside the UPS cabinet after the upstream input feeder circuit breakers are opened because of the installed internal batteries. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality 6-15...
Power is present inside the UPS cabinet after the upstream input feeder circuit breakers are opened because of the installed internal batteries. Activated Deactivated Pushbutton locked into place Unlock pushbutton to release Figure 6-8. REPO Operation 6-16 Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
The paragraphs in this section provide operating instructions for a UPS system containing multiple UPSs. NOTE 1 If an External Battery Cabinet (EBC) is installed, refer to the Eaton 9E External Battery Cabinet Installation Manual listed in paragraph 1.7 for EBC battery breaker location.
Page 94
RETURN pushbutton. The critical load is immediately supplied by the bypass source, in Bypass mode from all UPSs. The BYPASS status indicator is illuminated. 6-18 Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
On the UPS System Control screen, select the HE: ENABLE DISABLE command, then press the RETURN pushbutton. All of the UPSs transfer to Standard Normal mode. The NORMAL status indicator is illuminated. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality 6-19...
If EBCs are installed, close the battery breakers. On the UPS being restarted, observe the UPS control panel display becoming active, indicating logic power. 6-20 Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
If the UPSs are dual-feed, open all bypass feeder circuit breakers. If the UPSs are EBC capable, open all UPSs battery breakers. 10. If EBCs are installed, open all battery breakers Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality 6-21...
UPS mode, then press the RETURN pushbutton. The Verify Action screen is displayed, providing a choice to proceed or abort the shutdown. 6-22 Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
CAUTION Do not attempt to restart the system after the REPO until the cause of the shutdown has been identified and cleared. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality 6-23...
Page 100
Restart the UPS by following the procedure in paragraph 6.4.1 or 6.4.2. WARNING Power is present inside the UPS cabinet after the upstream input feeder circuit breakers are opened because of the installed internal batteries. 6-24 Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Chapter 7 Communication This chapter describes the communication features of the Eaton 9E UPS. For terminal wiring information, see paragraph 3.2.3 and paragraph 4.11. For location of the customer interface panel and terminals, see Figure 4-10 and Figure 4-11. Mini-Slot Cards The Eaton 9E UPS has two standard, factory-installed Mini-Slot communication bays.
Page 102
Communication This page intentionally left blank. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Do not dispose of batteries in a fire. Batteries may explode when exposed to flame. Do not open or mutilate batteries. Released electrolyte is harmful to the skin and eyes. It may be toxic. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
Check the UPS air filters (located behind the front door) and wash or replace as necessary. See Figure for filter location. The filter size is 16.5" x 45.5" × 0.25". Contact an Eaton service representative for replacement filters. To remove the filters: CAUTION Verify washed filter is thoroughly dry before reinstalling.
8.2.4 ANNUAL Maintenance Annual preventive maintenance should be performed only by authorized service personnel familiar with maintenance and servicing of the UPS system. Contact an Eaton service representative for more information about service offerings. 8.2.5 BATTERY Maintenance Contact an Eaton service representative for battery maintenance.
Maintenance Training A basic training course, available from Eaton Corporation, gives you a competent working knowledge of the UPS system operation and teaches you how to perform first level corrective maintenance. For more information about training and other services, contact the Help Desk (see paragraph 1.7).
4 kV OC, 3 kA SC per ANSI 62.41 and IEC 8014 Battery Voltage 216 Vdc 20A maximum at any load up to100% load (supports internal and internal Battery Charging Capacity plus external battery configurations) Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
20 kVA 12.0 9E–30/20 20 kVA 22.0 9E–30/30 30 kVA 12.0 NOTE Battery times are approximate and vary depending on the load configuration and battery charge. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
30 kVA 9E 30EBC 45.6 9E–30/30 30 kVA 9E 30EBC 84.5 NOTE Battery times are approximate and vary depending on the load configuration and battery charge. Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1 www.eaton.com/powerquality...
For Product installed (and currently located) outside the fifty (50) United States and the District of Columbia, if, in the opinion of Eaton, a Warranted Item is defective, Eaton's sole obligation, at the option of Eaton, will be to refurbish or replace such defective Warranted Item (not including the costs of labor coverage). The defective Warranted Item will be refurbished or replaced onsite at the End-User's location or such other location as determined by Eaton.
Page 112
Eaton shall not be responsible for failure to provide service or parts due to causes beyond Eaton's reasonable control. In no case will Eaton's liability under this Warranty exceed the replacement value of the Warranted Items.
Need help?
Do you have a question about the 9E Generation 3 and is the answer not in the manual?
Questions and answers