Commisioning

.04
Fig. 8 - 04
● Before commissioning the machine, clean it thoroughly and lubricate it, or pour in oil,
see Chapter 12 Care and Maintenance!
● The machine, in particular the electric wires and pneumatic connection tubes, must be
examined for any damage.
● Have skilled personnel check if the machine can be operated with the available mains
voltage.
● Connect machine to the compressed air system.
The manometer on the air fi lter/lubricator unit must display a pressure of 6 bar.
If necessary, set to the correct value (see chapter 12.06 Checking / regulating air
compression).
Mounting and commissioning the machine
Do not operate the machine if there is any discrepancy.
The machine may only be connected to an earthed socket!