Configuring Webhmi; Configuring Webhmi For Sequence Control - ABB COM600 series User Configuration Manual

Substation management units 5.1 sequence control
Hide thumbs Also See for COM600 series:
Table of Contents

Advertisement

1MRS755001
5.
5.1.
COM600 series 5.1
Sequence Control Configuration Manual

Configuring WebHMI

Configuring WebHMI for sequence control

This section describes the steps involved in configuring WebHMI for the sequence
control functionality. Before starting the WebHMI configuration for sequence control,
the required communication parameters and the associated data connections needed for
the single line diagram functionality should already be configured in the SAB600 project.
For more information on WebHMI configuration, see COM600 HMI Configuration
Manual.
To configure WebHMI for sequence control:
1. In SAB600, right-click the Substation object in the Substation Structure and select
New > Functional > Sequences to add a sequence voltage level to the Substation
structure, see Figure 5.1-1.
Figure 5.1-1 Adding sequences to the substation structure
2. Assign a name to the added sequence voltage level by editing the Caption parameter
in the object properties window.
3. Add a sequence bay object to the added sequence voltage level by right-clicking the
sequence voltage level and selecting New > Functional > Sequence.
4. Rename the added sequence bay object to correspond the sequence name.
SAB600_SC_Substation_Sequence.png
41