Run Meter Test - Radian RD-30 Operation Manual

Portable three-phase electricity standard
Table of Contents

Advertisement

Operating System and Structure
8.8 Run Meter Test
A single tap on the Run Meter Test icon opens the following window.
In the Meter Test window, the user defines and sets up the type of meter test to run. In the DUT
tab, the meter under test serial number, Kh value, pulses out per Kh value, and the number of ele-
ments are all entered. In the same window, the user selects the number of Standard Elements being
used for the meter test, if a meter Sensor is being used, and if a single or polyphase meter test is to
be performed. Phase may be set as Phase A for DUT 1, Phase B for DUT 2, or phase C for DUT
3, or Total for any of the DUT's. The user selects the type of meter test to run. The user can select
to test FL – Full Load, PF – Power Factor, LL – Low Load, or a Demand test. The user can define
the meter function to be tested, the number of test pulses required for completion of the test, the
Demand time for a Demand Test, and if the test is to be designated as an As Found or As Left test.