General Installation Guidelines

Switch Chassis

The switch is designed to be installed in a standard 19-inch equipment rack.
Before continuing with switch installation, first review the general guidelines and
switch cooling requirements in this chapter.
This chapter includes these sections:
"General Installation Guidelines" on page 24
"How to Install the Switch in a Rack" on page 25
"Optional Expansion Module" on page 30
"How to Install an Optional Expansion Module" on page 30
Be sure to follow the guidelines below when choosing a location.
The installation location should:
be able to maintain its temperature within 0 to 50 ° C (32 to 122 ° F) and its
humidity within 10% to 90%, non-condensing.
provide adequate space (approximately five centimeters or two inches) on
all sides for proper air flow.
be accessible for installing, cabling and maintaining the device.
allow the status LEDs to be clearly visible.
Make sure twisted-pair cable is always routed away from power lines,
fluorescent lighting fixtures and other sources of electrical interference, such as
radios and transmitters.
Make sure that the unit is connected to a separate grounded power outlet and
is powered from an independent circuit breaker. As with any equipment, using
a filter or surge suppressor is recommended. Verify that the external power
requirements for the switch can be met as listed under
page
32.