4.1 Single UPS operation

1. Make sure A, B and C phase sequences are correctly connected and then supply power
to UPS.
2. Turn on the breaker of the battery bank (make sure that the
+ ,
N
and
-
of
terminal bay are in accordance with those on the output of the battery bank).
3. Switch on
input breaker
(Line input breaker: Main
; bypass input breaker:
Main
; line input breaker for 60K/80K standard models) on the UPS and fans start to
rotate for UPS self-inspection. Main menu can be accessed within about 4sec and then
operations should be carried.
Remark: the following drawing takes 3C3 EX 20KS as an example and statistics
are only for reference.
1) Power on
2) Automatic access within about 4s
19