4.2 Preparing the cable insertion

There are two possibilities available for the cable insertion:
Cable insertion from above (surface cable routing)
Cable insertion from behind (flush-type cable routing)
Preparations
Remove the connector panel cover (see Chapter "Removing/mounting the cable panel
cover").
Populate the charging station with the required cable glands or seals (if an open cable
insertion opening is not used any more).
Breaking out the cable insertion openings
Installation
Breaking out the cable insertion openings
Place the housing on on a stable support
pad and use a hammer and flathead
screwdriver to carefully break out the
required cable insertion openings.
Then insert the corresponding
feedthroughs (cable glands or double-
membrane seals)