Procedure
Carry out the following steps for each OS project:
1. In the SIMATIC > WinCC > Tools submenu of the Windows Start menu, select the menu
2. Click "Next".
3. Select the MCP file in the project path for the OS.
4. Click "Finish" in "Step 3 of 3".
5. Repeat these steps for every OS of your PCS 7 project.
Additional information
● Online help
● Online help
● Configuration Manual
6.2.5

How to Check the PH Consistency

This step shows you if all the data in the plant hierarchy is consistent.
Requirement
● The project in SIMATIC Manager is open in the plant view.
Procedure
The following steps can be performed for the multiproject or for each individual project (in the
multiproject).
1. In the tree view, select the object to be checked (e.g., the multiproject).
2. Select the Options > Plant Hierarchy > Check Consistency command.
3. If errors are found, make the appropriate corrections.
Software update without utilization of new functions
Service Manual, 03/2012, A5E02779792-02
command "Project Migrator".
The "CCMigrator" dialog box opens with "Step 1 of 3".
"Step 2 of 3" opens.
OS projects are located in the PCS 7 project path under "wincproj".
The update is performed automatically.
WinCC Information System > Migration
WinCC Information System > Working with WinCC > Archiving process values
The program checks the PH.
The "Check Consistency – Log" dialog box opens.
Note
If you need information on the possible errors, click the "Help" button in the "Check
Consistency - Log" dialog box.
Process Control System PCS 7; Operator Station
Adaptations in the PCS 7 project on the ES
6.2 General adaptations
37

Advertisement

Table of Contents
loading

Table of Contents