Check List - Siemens SINAMICS G120 Getting Started

Hide thumbs Also See for SINAMICS G120:
Table of Contents

Advertisement

3

Check List

Before power is applied to the inverter/motor system, the following checks should be
performed:
Check that:
1
The environmental conditions conform to the inverter/motor specifications
2
The inverter and the motor are securely mounted
3
The inverter and motor are correctly installed with adequate cooling provision
4
The motor and the application/equipment are ready to start, i.e. safe state - motor can
rotate
5
The inverter is correctly earthed/grounded
6
The input power (supply) voltage matches the inverter's nominal input voltage
7
The input power (mains) fuses are the correct type and installed correctly
8
The motor connections are connected to ensure the correct direction of rotation of the
motor at start-up
9
The motor and mains connections are connected and tightened to the required
specification
10
The motor connections are not reversed - the motor will start but serious damage may
occur to the connected equipment
11
The motor cable is routed away from other cables
12
The control connections are connected and tightened to the required specification
13
No tools or other objects that can cause damage to the system are present
14
The inverter is the only power source to the motor
CU240E
Getting Started, 10/2007, A5E01301680B AA
11