The basic commissioning wizard ends with the following dialog:
To complete basic commissioning, the motor data identification, selected during basic
commissioning must be performed via switching on the inverter. This can be done via
the chosen command source (e.g. terminals, BOP or communication) or via STARTER
as shown in the dialog box below.
Motor Data identification via STARTER
First click "Control panel" to open the dialog, then press "Assume control priority"
(when connected via PC connection Kit, select BOP link (RS232) (the "assume-button"
changes to "Return") and select "Enables". Now the ON and OFF buttons get active.
Press the ON button start the Motor data identification. While Motor data identification
is active, the
CU240E
Getting Started, 10/2007, A5E01301680B AA
-button is disabled and in the alarm 541 "Motor Identification active"
Commissioning
23