Testing

Prior to patient placement, the following test procedures should be performed
to make sure air mattress control unit and air mattress installation are
complete:
1. Plug the power cord into power outlet.
2. Turn the air mattress control unit on by pressing and holding the
power button on the control panel and allow the mattress to inflate.
The mattress should fully inflate in no more than three minutes. The
mattress section LEDs on the control unit panel will blink whilst the
mattress inflates. When the mattress is fully inflated the LEDs will stop
blinking.
3. If the mattress does not inflate or an air leak is heard, check that the
CPR valves are closed. Check for a leak at the mattress to frame
connection point. Refer to Attach Integrated Air Mattress Section,
figure 7, to tighten this connection.
4. At one of the bed control panels, raise the backrest angle to above
30° as indicated on the weigh panel display. Verify that the >30°
indicator is lit on the Air Mattress Control unit.
5. Raise all of the side rails. Put the head right side rail into the lowered
position and verify that the appropriate side rail down indicator
is lit on the Air Mattress Control unit. Raise the side rail. Repeat
this procedure for the other three side rails. Lower backrest to
approximately 15°.
6. Press the patient turn right button. Wait a few seconds to verify the
mattress has begun to turn. Put one of the right side rails into the
lowered position and verify that the alarm is heard and the mattress
starts to return to a level position. Verify the side rail down and alarm
indicators are both lit and the nurse turn right indicator is blinking.
Press the alarm silence button to acknowledge and clear the alarm.
7. Press and hold the CPR button on the attendant control panel. Verify
that the bed deck flattens (if in an articulated position), the CPR
valves open, the air mattress deflates and the Air Mattress Control
unit turns off.
8. Press the power button on the Air Mattress Control Unit and allow the
mattress to fill.
9. Raise backrest to approximately 15°, pull CPR handle on the side
of the bed frame. Verify that the backrest flattens (if in an articulated
position), the CPR valves open, the air mattress deflates and the Air
Mattress Control unit turns off.