Figure 43 - Disengaging Locking
Latch
Figure 44- Shaft Fully Extended
Page 52
Waukesha Cherry-Burrell
6. Unlatch locking latch.
7. The head has an ON-OFF engraving on the rim, located just
above product outlet. Rotate head in OFF direction until head
disengages.
8. Lower head until hydraulic rod is fully extended. See Figure
44.
9. Once shaft is in down position, blades may be removed from
shaft.
NOTE: Blades should be kept in the same position on mutator
shaft throughout life of blade. Make sure blades are removed and
reinstalled in the same location on shaft.
10. If shaft is to be removed from unit, lift head and shaft off lift
pin and move head away from unit while a second person
guides spline end of shaft out of unit.
11. Place shaft and head assembly on a table or suitable frame
for servicing.
12. Scraper blades can be removed and serviced at this time.

Shaft Installation - Vertical Unit

1. Check the condition of the O-ring in the head and lubricate
lightly. Assemble head to shaft if necessary, following
procedures under "Shaft Installation - Horizontal Unit" on
page 48.
2. Assemble head to shaft.
3. Apply anti-seize compound to the drive end splines and the
next 3 inches of stub shaft length.
4. Slide splined end of shaft into unit.
5. Lift head onto lift pin.
Figure 45 - Head Installed on Pin
6. Install scraper blades.
NOTE: Blades should be kept in the same position on mutator
shaft throughout life of blade. Make sure blades are removed and
reinstalled in the same location on shaft.