Instructions for Connecting the Cables
The procedure for connecting the cables is as follows:
Checking the Cable Route
Attaching to the Connector
Attaching Name Tags
Checking the Cable Route
When installing a cable between the Outdoor AP and other devices, such as the AC
distribution box, MGB (main ground bar), or a switch (or router), you must check the cable
route, length, and cable installation method.
Consider the following steps while checking the cable route:
Select a minimum cable length within a range that does not affect cable installation or
maintenance.
The cable must be installed in a location where it will not be damaged by external
factors, such as power lines, flooding, footpaths, etc.
Samsung Electronics America
Cutting the Cable
Installing the Cable
Binding the Cable

Figure 32. Procedure for Connecting the Cables

The system must not be connected with connectors when installing cables after
cutting. When the system is connected with connectors while installing cables, it
can cause damaged connectors or bad connections through tension or operator
mishandling.
The sequence for cutting the cables and installing the cables can be changed
depending on the site situation, such as cutting after installing or installing after
cutting.
When assembling
connectors at the site
Version 1.0
Assembling Connector
Page 48 of 117