Roofing Installation for 4 x 6
24. Install roofing, starting from back of the room. The back edge of the first panel should be flush with
the back edge of the ceiling panel. Install the roof panel to have a minimum of 1" and a maximum of
2" overhang at the bottom of the panel along the fascia.
Overlap 2 ridges
25.
Secure the back roof panel with two screws. Do not overtighten the screw
as it will deform plastic ridge.
Note: Outer edges of the roof panels are secured by the fascia and ridge cap.
26.
Overlap 1 ridge of the middle panel on the back panel and install the screws.
27.
Overlap two ridges of the front panel over
the middle panel. Front panel should be flush
with the front edge of the ceiling. Install the
remaining screws.
28.
Repeat the process on other side of ceiling
710-0131
Rev. 02
Overlap 1 ridge
Page 10 of 16
Minimum of 1-inch overhang.