Starting the appliance

Complete the installation by switching on the appliance and running the power-on
diagnostics. Each time the appliance is switched on, it runs a self-testing program
to ensure that it is running correctly. See Figure 12 for the locations of the
Information LED, System Error LED, POST Complete (OK) LED, and Power-on

LED.

Note: Depending on the system status, other LEDs may be on.
Figure 12. Locations of the Information LED, System Error LED, POST Complete (OK) LED,
and Power-on LED
If a problem is detected during the diagnostics, refer to the IBM TotalStorage
Network Attached Storage Models 200 and 225 Service Guide.
After you plug the power cord of the appliance into the power supply and an
electrical outlet, start the appliance by pressing the power button on the front of the
appliance.
Note: After you plug the power cord of the appliance into an electrical outlet, wait
Attention:
upon start up. The first time you start the appliance, a series of configuration and
system preparation programs that finish configuring the NOS are run automatically.
These programs must finish running before you use any included applications to
connect to or configure your appliance. Wait at least 5 minutes to connect to or
configure the appliance after the initial system start.
3
4
OK
TX
100
LINK
MB
OK
RX
1
Information LED
2
System Error LED
3
Power-on LED
4
POST Complete (OK) LED
approximately 20 seconds before pressing the power button. During this
time, the system-management processor is initializing and the power button
does not respond.
The operating system undergoes a series of initialization operations