Installation Workflow

When installing the StorEdge system, follow this workflow to ensure all the components are connected 
and functioning correctly.
Step 1 - PV system installation - modules, power optimizers and inverter:
 
Power optimizers - as described in Installing the Power Optimizers on page 13.
l
 
Inverter - as described in Installing the Inverter on page 21.
l
Step 2 - SolarEdge Auto-transformer and AC load panel installation (required for Backup Power only): 
Refer to Auto-transformer and Backed-up Loads Panel Installation (for Backup) on page 28.
Step 3 - Electricity Meter installation (required for Smart Energy Management only). Refer to Meter 
Installation  on page 30. 
Step 4 - Connecting PV strings (DC) to the inverter - Refer to Connecting the Strings to the Inverter on 
page 33.
Step 5 - Connecting the battery to the inverter and mounting the battery. Refer to the installation 
information in the manufacturer documentation, and to StorEdge Inverter Connections on page 31.
Step 6 - Connecting all components to the inverter - connect the auto transformer and loads (AC), PV 
strings (DC), and meter. Refer to StorEdge Inverter Connections on page 31.
Step 7 - Commissioning the inverter - Activate the system and pair the power optimizers. Refer to 
Commissioning the Installation on page 44.
Step 8 - Connecting to the monitoring platform. Refer to Setting Up Communication to the Monitoring 
Platform on page 69.
Step 9 - System Configuration - Configuring the RS485 bus and StorEdge applications. Refer to System 
Configuration on page 78.
The following flowchart appears throughout this Installation Guide to assist with the installation steps:
SolarEdge-StorEdge Installation Guide MAN-01-00262-1.2