Installation Workflow

When installing the StorEdge system, follow this workflow to ensure all the components are connected 
and functioning correctly.
Step 1 - PV system installation - modules, power optimizers and inverter:
 
Power optimizers - as described in Installing the Power Optimizers on page 10.
l
 
Inverter - as described in Installing the Inverter on page 17.
l
Step 2 - SolarEdge Auto-transformer and AC load panel installation (required for Backup Power
only): Refer to Auto-transformer and Backed-up Loads Panel Installation (for Backup Only) on page 24.
Step 3 - Electricity Meter installation (required for Smart Energy Management). Refer to Electricity 
Meter Installation     on page 26. 
Step 4 - Connect the battery to the inverter and mount the battery
information in the manufacturer documentation, and to StorEdge Inverter Connections on page 27.
Step 5 - Connect all components to the inverter - connect the auto transformer and loads (AC), PV 
strings (DC), and meter. Refer to StorEdge Inverter Connections on page 27.
Step 6 - Commissioning the inverter - Activate the system and pair the power optimizers. Refer to 
Commissioning the Installation on page 55.
Step 7 - Configuring the StorEdge application. Refer to Configuring StorEdge Application on page 65.
Step 8 - Connecting communication between the inverter and monitoring portal. Refer to Setting Up 
Communication to the Monitoring Portal on page 71.
The following flowchart appears throughout this Installation Guide to assist with the installation steps:
1 To gain better accessibility to the battery connection panel, it is recommended to connect the battery cables
mounting it on the wall.