b. If you plan to manage the server modules through the modular system CMM,
c. Ensure that the modular system chassis is powered on and running.
d. Ensure that the modular system is running the latest version of Oracle's
Note – For more information about preparing the modular system and the CMM
ILOM, refer to the Sun Blade 6000 Modular System Installation Guide.
2. (If necessary) Upgrade all SAS-1 components.
This server module is a SAS-2 component. You must upgrade the firmware of all
SAS-1 components (such as SAS-1 NEMs and disk modules) to a firmware version
that supports SAS-1/SAS-2 coexistence. You must complete this firmware upgrade
before you insert this server module or any other SAS-2 component into the
modular system chassis. Refer to the SAS-1/SAS-2 Compatibility Upgrade Guide for
more information. See
3. Unpackage the server module.
Be ready to insert the server module within 60 seconds of removing the filler
panel.
4. Install any optional components.
See
5. Be prepared to communicate with the server module as quickly as possible after
completing the physical installation.
As soon as you insert the server module in a powered modular system, power is
supplied to the server module and the SP generates messages. If you want to see
these messages, be ready to connect using one of the methods in
Communication With the Server Module During Installation" on page
Related Information
"Install Optional Components" on page 23
"Insert the Server Module Into the Chassis" on page 23
22
SPARC T4-1B Server Module Installation Guide • May 2012
configure the CMM to run in your network.
CMM ILOM firmware.
"Related Documentation" on page
"Install Optional Components" on page
v.
23.
"Plan
15.

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the SPARC T4-1B and is the answer not in the manual?

Questions and answers

Table of Contents